In a situation where drawings conflict with written documents, which takes precedence?

Drawings

Written documents

In the context of construction documents and contracts, written documents generally take precedence over drawings in cases of conflict. This is because written documents, such as specifications, provide detailed requirements and standards that govern the project. These documents often include critical information regarding materials, products, installation methods, and performance criteria that are essential for compliance with the overall design intent and quality assurance.

Additionally, written contracts outline the obligations of all parties involved and provide the legal framework for the project. If any discrepancies arise between the drawings and the written documents, it is important to consult the specifications or contract language to determine the correct interpretation. This hierarchy ensures clarity and accountability in interpreting the project requirements, minimizing ambiguity that could lead to misinterpretations or construction errors.

Shop drawings and submittals, while important for demonstrating compliance with the design intent, typically follow the established requirements set forth in the written documents. Hence, they do not have the same precedence as the specified written requirements. Understanding this hierarchy is crucial for interior designers who must navigate these documents effectively during a project.

Shop drawings

Submittals